9/6/2022
-We will be starting to put down cold patch (filling potholes) on various roads starting week of 9/19
-Beginning week of 9/26 we will begin work on some of our gravel roads ie, Ratcliff, Riddle and Cemetery roads
9/12/2021
We have yet to get a schedule for chip seal but will post as soon as available.
8/10/2021
We are continuing road prep work, patching pot holes and adding asphalt grinds to build up roads.
We do not have a chip seal schedule as of yet, as soon as available it will be posted.
7/6/2021
Prep work and ditching is in progress on Albright Rd. and should complete this week.
- Week of 7/12/2021 will be starting repair, ditching and prep to Clark Hollow.
- Week of 7/19/2021 will begin work on Radcliff hill , ditch , grade and fill.
6/2/2021
Prep work to Wilt rd, Albright, Riddle and Allison rd are almost complete this work is being done to get ready for Chip and seal that will be contracted with county this year. It is expected to be complete by August 2021.
Next step will be to add aggregate to the above mentioned rds.
We want to thank Everyone for there patience and understanding with the debris that was left behind , we will clean up.
In addition to the above roads Lipscomb, Clark and Eastfork roads will also get resurfaced this year.
10/5/2020
chip and seal work complete on Dixon ,Stevens and Gearing Ridge
9/2/2020 Update
Chip Seal will start Tuesday 9/14/2020 weather permitting on the following rds
Dixon Mill
Stevens Branch
Gearing Ridge
6/28/2020 Update
- Replacement of culverts on Dixon Mill are complete
- Installation and replacement of culverts on Gearing Ridge are complete
- Thank you for everyone’s patience and understanding during temporary road closure
- Next will be Stevens Branch for culvert installation on Monday 6/29/2020
- Update 6/23
- Work to begin 6/25 /2020 on Dixon Mill
The following 3 roads will be chip and sealed this year in Eagle Twp, if budget allows additional roads will be added.
Dixon Mill
Gearing Ridge
Stevens Branch
Work will be performed in that order. The first step will be to prep each of these roads for the chip & seal because of there condition. Prep will consist of replacing or adding culverts to roads ,ditching and grading. Aggregate will then be applied to road to improve condition.
After approximately two week waiting period the chip & seal will be applied finishing road.
At this time work is to start week of 6/22/2020 on Dixon Mill.
I will try to add photos to photo gallery of work progress.
Eagle Township Road Inventory
- Albright Road
Allison Road
Carmel Road
Cemetery Road
Clark Hollow Road
Dixon Mill Road - East Fork Road
Gearing Ridge Road
Gibson Hollow Road
Haynes Hollow Road
Lady Run Road
Lipscomb Road
Maxwell Road
McGee Road
Peck Lane
Ratcliff Hollow
Riddle Road
Steven’s Branch Road
Wilt Road